Construction progress for January 2024

1 section
- Preparations for the distribution of the gas network inside the section have been completed
- Elevator cabins were installed and sheathed

2 section
- We are finishing the preparation for the gas network distribution inside the section.
- Elevator cabins were installed and sheathed

Decorative plaster has been applied to the staircase and its painting is being completed. We also finish the facades of commercial premises.